Menu
Projects
View Project Details
Ontario, Canada
EPC / Design Build Contractor
Total Design & Construction of All Work Associate with this 400MW Simple Cycle Peaking Plant Utilizing Siemens SGT6 5000 F4 Technology
View Project Details
Waterbury, CT
EPC / Design Build Contractor
100MW Simple Cycle Power Plant Utilizing (1) GE LMS-100 CTG
View Project Details
Middletown, CT
Major Mechanical Contractor
650MW 2x1 Combine Cycle Plant Using (2) Siemens STG6-5000 F3 CTGs with (2) Vogt HRSGs and (1) Siemens STG. Lill Self Performed Over 1.3M Direct Hire Man Hours with Zero Lost Time Accidents
View Project Details
Hunlock Creek, PA
General Contractor
150MW 2x1 Combined Cycle Power Plant Using (2) GE-LM6000 CTGs and (2) Victory HRSGs
View Project Details
New Johnsonville, TN
General Contractor
New Construction of 320MW Simple Cycle Plant Utilizing (4) GE Frame 7EA Combustion Turbines in Simple Cycle
View Project Details
West Springfield, MA
EPC / Design Build Contractor
100MW Simple Cycle Power Plant Utilizing GE LM-6000 CTGs
View Project Details
Dundee, IL
General Contractor
Greenfield Construction of a 260MW Gas Fired Peaking Plant Siemens/Westinghouse 501D5A & GE LM5000 Combustion Turbine Technology
View Project Details
Newington, NH
Major Mechanical Contractor
Total Mechanical Erection of a 575MW Combined Cycle Facility Utilizing (2) GE 7FA CTG’s, (2) Foster Wheeler HRSG’s, and a GE 235MW STG
View Project Details
Philadelphia, PA
Total Mechanical Contractor
173 MW Combined Cycle 1x1 Cogeneration Facility Utilizing a Siemens/Foster Wheeler 501-D5A CTG Nooter Erickson Double Wide HRSG and 720K #ST/HR Cerrey Field Erected Boiler