PROJECT OWNER
Niagara Mohawk Power Corporation
PROJECT NAME
Dunkirk Major Planed Outages 1987/1993
LOCATION
Dunkirk, NY
ROLE
Major Outage Contractor
PROJECT YEARS
1987 & 1993
Dunkirk Steam Station
Frank Lill & Son, Inc. removed and replaced 126 horizontal primary superheater elements and 32 superheater connecting tubes on a 180 MW CE coal boiler at the Dunkirk generating station. The project included over 1,000 field welds plus asbestos abatement, refractory installation, and insulation installation.